Maintenance Question 7

We have to take gypsum out of a rectangular silo and we are not sure if a rotary valve is necessary between the silo and a screw conveyor. At the moment we have problem of ratholing and bridge as well, thanks in advance for any help.

Reply


Know the answer to this question? Join the community and register for a free guest account to post a reply.

admin
1156 posts
TimePosted 22/08/2006 10:21:24
admin says

Re: Maintenance

I would suggest installation of an acoustic cleaner and sounding the horn periodically to combat the ratholing problem.

Reply

admin
1156 posts
TimePosted 22/08/2006 10:21:24
admin says

Maintenance Question 8

We carry out refractory work with screw jacks, maximum 10m lining at a time (ie 5m maximum simultaneously at two different locations in same kiln). As ours is a small plant of 1000tpd, with single kiln of 64m length, deploying a brick lining machine and dismantling machines are not viable in terms of cost for us. What therefore is the maximum length of refractory work can be done at a time, in how many parts, simultaneously, from the various aspects such as safety, life of refractory etc.

Reply

admin
1156 posts
TimePosted 22/08/2006 10:21:24
admin says

Re: Maintenance

I would recommend using the glueing method rather than screw jacks and then you can replace as long a section as you like without the concern of installing and removing the jacks. My understanding is that the glueing method will have no problems with a kiln of 3.95m diameter. However, you would be better to check this with suppliers of the refractory glue when placing your order.