Refractory Installation

I wanted to know which the standard of refractory installation with a bricking machine considering the diameter of the kiln (for example 5 m).

Does exist a reference in meters/day?. The value that I need is from the beggining (with the areas to change cleaned) to finishing the complete job.

Reply


Know the answer to this question? Join the community and register for a free guest account to post a reply.

erdosel
1 posts
TimePosted 21/07/2008 09:02:40
erdosel says

Re: Refractory Installation

in my experience for a new kiln it s about 6 full day (6*24 dours)

but for friction of kiln coat it may take 10 days becouse of the shape of deformation.

 