Topaz completes RAK Cement project, UAE

Topaz completes RAK Cement project, UAE
30 August 2009


Ameinfo reported that Topaz Engineering has successfully installed and commissioned complete Electrical and Instrumentation works in the Coal Mill building for RAK Cement.

One of the key highlights of the project was the safe completion of 78,000 man hours without any lost time injury.

Topaz has executed the E&I work on a turnkey basis which included the supply, installation and testing of cables, cable trays, profibus cables, MLDB panels and light fittings in the total Electrical and Instrumentation package.

The contract also comprised the installation of 11 KV sub stations with HV switchgear, distribution transformers and motor control centre panels for low voltage distribution, PLC panels and other control panels.

In addition to electrical and instrumentation works, the company also executed mechanical works comprising the fabrication and supply of static equipments like coal bins, bag filters, cyclones, interconnecting ducting, conveyor system totaling approximately 460 tonnes of fabrication and erection works within a very tight time schedule.
Published under Cement News