China National Building Materials (CNBM) - March 2018


Beijing Triumph International Engineering Co, part of the China National Building Materials (CNBM) group, and FLSmidth have received an order for a new 12,000tpd cement plant for ETHRB Group. The new works, which will be located in Relizane, Algeria, is due for completion by the end of 2020.

While Beijing Triumph International Engineering Co will be responsible for the construction of the plant, FLSmidth will be supplying the equipment, including two ATOX® raw mills, two preheaters (two-string inline calciner, five stages), two kilns, two Cross-Bar® coolers and three OK 61-4 cement mills.

The project is expected to take 37 months to complete with Mill 1 ready after 18 months, clinker production Line 1 after 26 months, cement Mill 2 after 29 months, clinker production Line 2 after 31 months and cement Mill 3 due to be completed after 34 months.