Cement mill 1st & 2nd chamber load

Dear Experts,

I read some where that in cement 2chamber ball mills 1st chamber grinding media

4.5 mt/m3 and in 2nd chamber it is more i.e. 4.6 mt/m3.

Could you send me the calculation for above in below mail Id

email:<dadhichss2004@yahoo.com>

Thanks with regardss,

Dadhich

Reply


Know the answer to this question? Join the community and register for a free guest account to post a reply.

fjalali
81 posts
TimePosted 13/12/2011 11:23:09
fjalali says

Re: Cement mill 1st & 2nd chamber load

Do the calculation based on ball diameter density and ball wieght

Ø Ball [mm] Density [t/m3]
 
80   4.40  
70   4.40  
60   4.40  
50   4.60  
40   4.60  
30   4.65  
25   4.70                     

Reply