In the corresponding period of 2010, Oman Cement produced 565,160t from its original two lines which have been operational for several years. The third kiln has a production capacity of 4000tpd.
Cement production during the January-June period was 950,553t, 3.9 per cent higher than the same period of 2010.
Oman Cement Company, expecting strong demand to continue, has signed contracts for the upgrade of old pollution control equipment and capacity upgrade of kiln No 1 at a cost of OMR14.27m (US$37.05m).
The company also has plans to increase its cement grinding capacity, tenders for which will be issued in the fourth quarter.