The two grinding plants installed at the Chanderia factory will each be equipped with a POLYCOM® high-pressure grinding roll with 2 x 1450kW drive and a SEPOL®-PC separator. The POLYCOM® units are to be installed upstream of the ball mills already existing at the factory. Grinding plant I has a rated cement output of 315tph, while grinding plant II has a rated cement output of 325tph.
The Satna factory will also receive a POLYCOM® high-pressure grinding roll with 2 x 1450kW drive and a SEPOL®-PC separator. In combination with the existing ball mill, the POLYCOM® will bring the grinding plant up to a rated cement output of 330tph.
Meanwhile, Zement- und Kalkwerke Otterbein GmbH & Co. KG has contracted Polysius to supply and install a new cement grinding plant at the Großenlüder-Müs works.
Polysius is to supply a 3.4m x 10.1m two-compartment mill equipped with a 1600kW COMBIFLEX® drive.