In total ABB will deliver six water cooled cycloconverters including the new control and regulation system AC800PEC. Two new water cooled cycloconverters with a power of 5900kW each will be implemented for the upgrade of the raw mills #1 and #2.
Additional four water cooled cycloconverters with a power of 5250kW each, will be delivered for the upgrade of the cement mills #1, #2, #3 and #4. Together with the six cycloconverters ABB will supply six chillers for the cycloconverter cooling.
Deliveries will be finalised in Q2 of 2010, while as installation and start-up of the system will take place in Q4 of 2010.