According to Sinoma International’s filing with the Shanghai Stock Exchange, this contract is complementary to an agreement signed between the two parties earlier.
The designed capacity of the cement production line is 6,000tpd, which is expected to be completed in 16 months. The total value of the contracts will reach EUR 96.69m.
In the statement, Sinoma also disclosed its Tianjin unit was awarded a RMB 868.73m contract by Lafarge Ruian Cement Co Ltd to build a clinker line in Guizhou province. The project is scheduled to be completed within 23 months.