Najran Cement has postponed the launch of its waste heat recovery (WHR) plant by six months, the company said in a bourse statement yesterday.
The Saudi-based cement producer will now bring the new WHR plant on line in March 2014 instead of September 2013 as originally planned. The project is costing US$45m with a projected power generating capacity of 27.1MW.