Ecebol Oruro plant to start production testing at end February

Ecebol Oruro plant to start production testing at end February
07 February 2019


Bolivia-based cement producer Ecebol is finalising construction of its plant at Jeruyo, Oruro. The company expects the start production tests at the end of the month. President Evo Morales is due to visit the plant’s facilities on Friday 8 February.

The plant has a packing capacity of 3600 bags/h and a production capacity of 1.3Mta of cement. While the plant uses German technology, some 96 per cent of labour used to build it is Bolivian. The project is under administration of the Development Service of Public Productive Enterprises (SEDEM).

Published under Cement News

Tagged Under: Bolivia Ecebol new capacity