Latest EPC kiln line upgrade project for Duna Drava

Latest EPC kiln line upgrade project for Duna Drava
26 June 2018


The 2400tpd Duna Drava Cement clinker line in Vác, Hungary, has been successfully re-commissioned and put into production in April 2018.

In less than two years, IKN completed the project on EPC basis.

The main target of the project was to adapt the pyroprocessing line to enable the use of up to 100 per cent RDF in the calciner. The two lower cyclone stages were replaced, a complete new preheater tower with the inline calciner was erected, a new bypass system as well as a new static inlet in the clinker cooler were installed.

The upgraded kiln line combines the latest industry practices with the most modern and up-to-date process technology.

Published under Cement News

Tagged Under: Hungary Duna Drava IKN upgrade