maw
10 posts
TimePosted 27/04/2014 12:43:08
maw says

kiln voulme loading

% loading = 1.5 Wt/LA

              =0.35 Wt/LA

              = 1.67 Wt/LA

which factor is correct , i found in one book of different editions diferent factors why it changed , from where this factor came ? any help !! ?

Reply


Know the answer to this question? Join the community and register for a free guest account to post a reply.

fjalali
81 posts
TimePosted 29/04/2014 12:37:45
fjalali says

re kiln voulme loading

Do you mean the volume load (specific load) as tpd/m3 of kiln?

Is used to be 4 now its 5-6 tpd/m3 at see level. FLS has 5 for 3-base kilns and 5.3 for 2-base kilns.

Hope it helps.

Reply