Key milestone reached in CI4C Project as commissioning nears
Schwenk Zement has confirmed that the last modular section of the Carbon Purification Unit (CPU) has been successfully installed at its Mergelstetten plant. With this installati...
4 posts · Page 1 of 1
Schwenk Zement has confirmed that the last modular section of the Carbon Purification Unit (CPU) has been successfully installed at its Mergelstetten plant. With this installati...
The work on the oxygen tank farm/liquid oxygen (LOX plant) on the CI4C site in Mergelstetten , Germany, is almost complete. The electrical engineering is expected to be complete...
The "Catch4climate" project reached another important milestone this week as it completed the installation of the six oxygen tanks for the oxyfuel plant. The oxyfuel kiln plant ...
Scherr+Klimke AG build 60m Catch4climate preheater tower in Germany A new milestone for the pilot project "Catch4climate" has been achieved with the completion of the 60m-high p...